Title
C12 - Change Order #1 for Fleming Island High School AICE Testing Facility
Description

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.  This change order is for owner requested items.  Specifically, to replace the failing storm water piping in the vicinity of the AICE Testing Building, relocate the water mains and a credit for the deletion of the knockdown ceiling finish in the restrooms.  The piping would be replaced regardless of the construction of the new building.

Gap Analysis

N/A

Previous Outcomes

The Construction Manager At-Risk is able to continue with construction for an on time completion.

Expected Outcomes

The Construction Manager At-Risk will proceed immediately with construction translating to an on time completion.  Storm drainage at Fleming Island High School will be replaced.

Strategic Plan Goal

Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. 

Recommendation

Approve Change Order #1 for the Fleming Island High School AICE Testing Facility.

Contact
Dr. Michael Kemp, Assistant Superintendent for Operations (904) 336-6825 michael.kemp@myoneclay.net
Financial Impact
The additional $184,682.00 will be from District Capital Outlay funds and is not a cost funded by Fleming Island High School.