Previous Item | Next Item |
|
||
March 3, 2022 - Regular School Board Meeting | ||
Title C23 - Spring Park Elementary School Guaranteed Maximum Price (GMP) Bid Package 2 (Building Construction and Site Work) | ||
Description In accordance with the School Board’s contract with Parrish McCall Constructors, Inc., for Construction Management At-Risk Services for Spring Park Elementary, Parrish McCall Constructors, Inc., presents to the School Board the GMP Bid Package 2 (Building Construction and Site Work). This Bid Package includes building construction and site work associated with Pre-Engineered Metal Building (PEMB) approved as GMP Bid Package 1. | ||
Gap Analysis The Agreement the School Board has with the Construction Manager (CM) At-Risk, Parrish McCall Constructors Inc., dated August 5, 2021, would be amended to establish a separate GMP for Bid Package 2 (Building Construction and Site Work). | ||
Previous Outcomes The CM At-Risk at Discovery Oaks Elementary utilized multiple GMPs to allow the site work to begin while the building design was being completed. | ||
Expected Outcomes GMP Bid Package 2 (Building Construction and Site Work) will allow construction to begin and ensure the foundations will be in place to accept the pre-engineered metal building ordered in GMP Bid Package 1. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve the Spring Park Elementary School Guaranteed Maximum Price (GMP) Bid Package 2 (Building Construction and Site Work). | ||
Contact Dr. Michael Kemp, Director of Facility Planning and Construction, (904) 336-6824, michael.kemp@myoneclay.net Mrs. Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact The GMP Bid Package 2 (Building Construction and Site Work) for this project is $31,789,658.00. These funds are available and budgeted in the Educational Facilities Plan. | ||
Review Comments | ||
Attachments GMP Bid Package 2 Spring Park Elementary School.pdf |