November 22, 2016 - Regular School Board Meeting | ||
Title C22 - Substantial and Final Completion of Window Replacement/Insulation Upgrade - Administration | ||
Description Establish a Substantial and Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The project, as determined by the Project Manager and Project Architect, has reached Substantial Completion in accordance with the project documents on September 29, 2016 and Final Completion on October 29, 2016. | ||
Recommendation Approve Substantial and Final Completion | ||
Contact John C. Merrill, Assistant Superintendent for Support Services | ||
Financial Impact None | ||
Review Comments | ||
Attachments Sub Completion Windows Admin.pdf Final Completion, Windows Admin.pdf |