Previous Item | Next Item |
|
||
November 4, 2021 - Regular School Board Meeting | ||
Title C17 - Schematic/Preliminary/Final (Phase I, II, and III) Plans and Specifications for Keystone Heights High School Renovate/Repair Baseball Press Box (Building 33) | ||
Description Each phase or a combination of phases is submitted to the School Board for review and approval. The plans have received staff review and are complete to Schematic/Preliminary/Final (Phase I,II, and III) stage. | ||
Gap Analysis Keystone Heights High School baseball press box (building 33) needs to be re-constructed. | ||
Previous Outcomes The school administration/departments have had the opportunity to express needs during plan review in order to design a project that will meet user's expectations. | ||
Expected Outcomes Schematic, Preliminary, and Final Plan review allows for participation from a variety of departments to ensure any program changes are incorporated into the design. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve Schematic/Preliminary/Final (Phase I, II, and III) Plans and Specifications for Keystone Heightgs High School Renovae/Repair Baseball Press Box (Building 33). | ||
Contact Dr. Michael Kemp, Director of Facility Planning and Construction, (904) 336-6824, michael.kemp@myoneclay.net Mrs. Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact The project estimate of $166,768.00 by Brian Boatright, Architect, is available and budgeted in the Educational Facilities Plan. | ||
Review Comments | ||
Attachments KHS Baseball Press Box Backup Information.pdf |