Title
C17 - Schematic/Preliminary/Final (Phase I, II, and III) Plans and Specifications for Keystone Heights High School Renovate/Repair Baseball Press Box (Building 33)
Description

Each phase or a combination of phases is submitted to the School Board for review and approval. The plans have received staff review and are complete to Schematic/Preliminary/Final (Phase I,II, and III) stage.

Gap Analysis

Keystone Heights High School baseball press box (building 33) needs to be re-constructed.

Previous Outcomes

The school administration/departments have had the opportunity to express needs during plan review in order to design a project that will meet user's expectations.

Expected Outcomes

Schematic, Preliminary, and Final Plan review allows for participation from a variety of departments to ensure any program changes are incorporated into the design.

Strategic Plan Goal

Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students.

Recommendation

Approve Schematic/Preliminary/Final (Phase I, II, and III)  Plans and Specifications for Keystone Heightgs High School Renovae/Repair Baseball Press Box (Building 33).

Contact
Dr. Michael Kemp, Director of Facility Planning and Construction, (904) 336-6824, michael.kemp@myoneclay.net
Mrs. Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net
Financial Impact
The project estimate of $166,768.00 by Brian Boatright, Architect, is available and budgeted in the Educational Facilities Plan.