| Title C30 - Substantial and Final Completion of Fleming Island High School HVAC Repair/Replacement | ||
| Description Establish a substantial completion and final completion date for audit purposes and as required by the State Requirements for Educational Facilities (SREF) and Florida Statutes. The project, as determined by the project manager and project architect/project contractor, has reached substantial completion on September 10, 2025, and final completion on October 17, 2025, in accordance with the project documents. | ||
| Gap Analysis N/A | ||
| Previous Outcomes N/A | ||
| Expected Outcomes N/A | ||
| Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
| Recommendation Approve Substantial and Final Completion. | ||
| Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director of Facility Planning and Construction, (904) 336-6852, lance.addison@myoneclay.net | ||
| Financial Impact None. | ||
| Review Comments | ||
|
Attachments FIH HVAC Repair - Substantial and Final Completion Certificate |