Previous Item | Next Item |
|
||
October 3, 2019 - Regular School Board Meeting | ||
Title C15 - Substantial and Final Completion of Grove Park Elementary Re-Roof Buildings 8, 9A and 9B | ||
Description Establish a Substantial and Final Completion dates for audit purposes and as required by the State Requirements for Educational Facilities (SREF) and Florida Statutes. The project, as determined by the Project Manager and Project Architect/Engineer, has reached Substantial Completion on July 30, 2019 in accordance with the project documents and Final Completion on August 13, 2019. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes N/A | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve Substantial and Final Completion. | ||
Contact Dr. Michael Kemp, Assistant Superintendent for Operations, (904) 336-6824, michael.kemp@myoneclay.net Bryce Ellis, Director of Facility Planning and Construction, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact None. | ||
Review Comments | ||
Attachments SubComp, GPE ReRoof Buildings 8, 9a and 9b.pdf FinalComp, GPE ReRoof Buildings 8 9A and 9B.pdf |