October 5, 2017 - Regular School Board Meeting
Title
C20 - Additive Change Order #1 for Middleburg High School Culinary Arts Renovations
Description

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.The additive changes are for Owner Requested Items (see attached).

Gap Analysis

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.  

Previous Outcomes

The additive changes are for Owner requested and/or unforeseen changes associated with renovations (see attached).

Expected Outcomes

Any owner requested and/or unforeseen items not included in the previously approved construction documents can be added and corrected in order to provide a safe and functional environment for stakeholders.  

Strategic Plan Goal

Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County Students.

Recommendation

Approve the Change Order.

Contact
Dr. Michael Kemp, Assistant Superintendent of Operations
Financial Impact
If approved, this Change Order will increase the contract amount by $13,075.41. The Substantial Completion date is August 31, 2017. Final Completion date is September 23, 2017. Architect fees will increase by $1,961.41 as a result of this change order.
Review Comments
Attachments
JustificationCO1, MHS Culinary Arts Renovations 10.5.17.pdf
CngOrder1, MHS Culinary Arts Renovations 10.5.17.pdf