Title C19 - Change Order #2 for Orange Park High School Stadium Repair/Replacement | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. This change order is for materials and labor for additional concrete foundation structures due to changed site conditions. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Construction will proceed immediately translating to an on time completion. | ||
Recommendation Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Contact Bryce Ellis, Assistant Superintendent Operations, (904) 336-6853, bryce.ellis@myoneclay.net, Michael Kemp, Director of Facility Planning & Construction, (904) 336-6824, michael.kemp@myoneclay.net | ||
Financial Impact This change order will increase the contract amount by $53,234.55. Architect fees, contracted at 7.91%, will increase by $4,210.85 as a result of this change order. These funds are available and budgeted in the Educational Facilities Plan. | ||