September 1, 2022 - Regular School Board Meeting | ||
Title C25 - Change Order #1 for Orange Park High School Stadium Repair/Replacement | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. This change order is labor and materials to provide temporary restroom facilities for school activities during construction. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve Change Order # 1. | ||
Contact Bryce Ellis, Assistant Superintendent Operations, (904) 336-6853, bryce.ellis@myoneclay.net, Michael Kemp, Director of Facility Planning & Construction, (904) 336-6824, michael.kemp@myoneclay.net | ||
Financial Impact This change order will increase the contract amount by $8,667.81. Architect fees, contracted at 7.91%, will not increase as a result of this change order. These funds are available and budgeted in the Educational Facilities Plan. | ||
Review Comments | ||
Attachments CO 1 OPH Stadium Repair.Replacement.pdf |