Title C43 - Additive Change Order #2 for Wilkinson Junior High School HVAC Replacement for Buildings 1, 4 & 5 | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.The additive changes are for Owner Requested Items (see attached). | ||
Gap Analysis Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. | ||
Previous Outcomes The additive changes are for Owner requested and/or unforeseen changes associated with renovations (see attached). | ||
Expected Outcomes Any owner requested and/or unforeseen items not included in the previously approved construction documents can be added and corrected in order to provide a safe and functional environment for stakeholders. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County Students. | ||
Recommendation Approve the Change Order. | ||
Contact Dr. Michael Kemp, Assistant Superintendent of Operations | ||
Financial Impact If approved, this Change Order will increase the contract amount by $4,777.30. The Substantial Completion date is August 4, 2017. Final Completion date is September 4, 2017. Architect fees will increase by $406.07 as a result of this change order. | ||