Title C24 - Change Order #1 for Ridgeview High School Re-Roof Buildings 7 and 10 | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. This change order is for the adjustment of materials. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve Change Order # 1. | ||
Contact Dr. Michael Kemp, Assistant Superintendent for Operations (904) 336-6824, michael.kemp@myoneclay.net Bryce Ellis, Director of Facility Planning and Construction, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact This change order will increase the contract amount by $16,850.00. Architect fees will increase by $1,432.25 as a result of this change order. These funds are available and budgeted in the Educational Facilities Plan. | ||