Previous Item | Next Item |
|
||
September 5, 2024 - Regular School Board Meeting | ||
Title C42 - Substantial Completion of Wilkinson Junior High School Fire Alarm Replacement | ||
Description Establish a Substantial Completion date for audit purposes and as required by the State Requirements for Educational Facilities (SREF) and Florida Statutes. The project, as determined by the Project Manager and Project Architect/Project Contractor, has reached Substantial Completion on August 19, 2024, in accordance with the project documents. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes N/A | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Substantial Completion for Wilkinson Junior High School Fire Replacement. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director for Facility Planning and Construction, (904) 336-6824, lance.addison@myoneclay.net | ||
Financial Impact N/A | ||
Review Comments | ||
Attachments Certificate of Substantial Completion for WJH Fire Alarm Replacement |