School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 P.M.
September 15, 2011 Regular Meeting with Public Hearing on Budget
Agenda Item #41


Item Title
C-29 Final Completion of Clay High School Roof Replacement Building 2 & 9/HVAC Rooftop Unit Replacement Buildings 1, 2, & 3

Issue/Rationale

Establish a Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. Final Completion was achieved on August 13, 2011.  The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects, Inc.), has reached Final Completion in accordance with the project documents.



Recommended Action
Approve Final Completion

Financial Impact
None

Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

 

Bryce Ellis, Facility Planning and Construction




Attachment:  CHS Roof.HVAC RTU Replacement Final Completion.pdf