March 6, 2025 - Regular School Board Meeting | ||
Title C32 - Substantial and Final Completion of Keystone Heights High School Safety & Security: Emergency Communications | ||
Description Establish a substantial completion and final completion date for audit purposes and as required by the State Requirements for Educational Facilities (SREF) and Florida Statutes. The project, as determined by the project manager and project architect/project contractor, has reached substantial completion on August 13, 2024 and final completion on February 14, 2025, in accordance with the project documents. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes N/A | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Substantial and Final Completion. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director of Facility Planning and Construction, (904) 336-6852, lance.addison@myoneclay.net | ||
Financial Impact None. | ||
Review Comments | ||
Attachments KHS Emergency Communications Certificate of Substantial & Final Completion. |