Title C19 - Change Order #1 for Wilkinson Junior High School Control Access | ||
Description Change orders are initiated by the contractor, architect/engineer or owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change orders are reviewed by the architect/engineer or staff prior to submission to the School Board for approval. This change order is for access control modifications, window shades, and protective film to the storefront. Six (6) additional calendar days will be added to the contract. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Change Order #1. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director for Facility Planning and Construction, (904) 336-6852, lance.addison@myoneclay.net | ||
Financial Impact If approved, this change order will increase the contract amount by $30,549.46. Architect fees contracted at 7% will increase by $2,138.46 as a result of this change order. These funds are available and budgeted in Educational Facilities Plan. | ||