Title C18 - Keystone Heights Elementary School New Cafeteria/Classrooms Guaranteed Maximum Price (GMP) Contract Award Bid Package #1 (Site Work) | ||
Description In accordance with the School Board’s contract with D.E. Scorpio Corporation, dba Scorpio, for Construction Management At-Risk Services for Keystone Heights Elementary School New Cafeteria/Classrooms, Scorpio, presents to the School Board the GMP Contract Award Bid Package #1 (Site Work). This Bid Package includes building construction and site work associated with storm drainage, paved play court, and playground equipment relocation. | ||
Gap Analysis The Agreement the School Board has with the Construction Manager (CM) At-Risk, Scorpio, dated February 3, 2022, would be amended to establish a separate GMP for Bid Package #1 (Site Work). | ||
Previous Outcomes The CM At-Risk at Discovery Oaks Elementary utilized multiple GMPs to allow the site work to begin while the building design was being completed. | ||
Expected Outcomes GMP Bid Package #1 (Site Work) will allow construction to begin and ensure an on time project completion. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve the Keystone Heights Elementary School New Cafeteria/Classrooms Guaranteed Maximum Price (GMP) Contract Award Bid Package #1 (Site Work).
| ||
Contact Dr. Michael Kemp, Director of Facility Planning and Construction, (904) 336-6824, michael.kemp@myoneclay.net Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact As budgeted in the Educational Facilities Plan for $889,398.00. | ||