Title C30 - Change Order #4 for Clay High School Gym Renovations | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. This change order is for Materials and labor to provide the installation of four new trap primers and a vapor retarder/primer for the designed installation of epoxy flooring due to the discovery of high moisture readings in current concrete flooring. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Change Order #4. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact This change order will increase the contract amount by $16,362.01. Architect fees, contracted at 8.82%, will increase by $1,443.13 as a result of this change order. These funds are available and budgeted in the Educational Facilities Work Plan. | ||