Previous Item | Next Item |
|
||
May 5, 2022 - Regular School Board Meeting | ||
Title C27 - Change Order #2 for Middleburg Transportation Fuel System Repair/Replacement | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. This change order is to supply materials and labor for the installation of required safety protection for above ground storage tank facility. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve Change Order # 2. | ||
Contact Bryce Ellis, Assistant Superintendent Operations, (904) 336-6853, bryce.ellis@myoneclay.net, Michael Kemp, Director of Facility Planning & Construction, (904) 336-6824, michael.kemp@myoneclay.net | ||
Financial Impact This change order will increase the contract amount by $9,505.00. Architect fees will increase by $807.93 as a result of this change order. These funds are available and budgeted in the Educational Facilities Plan. | ||
Review Comments | ||
Attachments CO 2 Middleburg Transportation Fuel System.pdf |