Title C28 - Change Order #2 for Wilkinson Junior High School Fire Alarm Replacement | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or owner, and may increase or decrease the project scope as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer or staff before submission to the School Board for approval. This change order is for the extension of the contract by six (6) days. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Change Order #2. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director of Facility Planning & Construction, (904) 336-6852, lance.addison@myoneclay.net | ||
Financial Impact If approved, this change order will not increase the contract amount. The Substantial Completion date will now be August 19, 2024. Final Completion date is September 13, 2024. Architect fees will not increase as a result of this change order. | ||