| Title C23 - Change Order #1 for Middleburg High School Parking Lot Renovations/Redesign | ||
| Description Change orders are initiated by the contractor, architect/engineer, or owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change orders are reviewed by the architect/engineer and staff prior to submission to the School Board for approval. This change order addresses design modifications and schedule acceleration due to regulatory delays in obtaining the St. Johns River Water Management District permit, adding 157 days to the contract. | ||
| Gap Analysis N/A | ||
| Previous Outcomes N/A | ||
| Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
| Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
| Recommendation Approve Change Order #1. | ||
| Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net, Lance Addison, Director of Facility Planning and Construction, (904) 336-6852, lance.addison@myoneclay.net | ||
| Financial Impact This change order will increase the contract amount by $458,913.53. Architect/Engineer fees, contracted at 6%, will not increase as a result of this change order. These funds are available and budgeted in the Educational Facilities Plan, pending Board approval. | ||
| Review Comments | ||
|
Attachments Change Order #1 C-64 2526 Revised-Board 20260618.pdf |