Title C40 - Change Order #1 for Ridgeview High School HVAC Repair/Replacement Building 3 | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer or staff prior to submission to the School Board for approval. This Change Order is for the replacement of two existing dampers. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Change Order #1. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director for Facility Planning and Construction, (904) 336-6824, lance.addison@myoneclay.net | ||
Financial Impact This Change Order will increase the contract amount by $28,777.46. These funds are available and budgeted in the Educational Facilities Work Plan. | ||